1. PS Exam Overview

Format, weights, and strategy

ItemDetail
ExamPrinciples & Practice of Surveying (NCEES)
Format100 multiple-choice questions
Duration7 hours to complete the exam, including tutorial and optional scheduled break
DeliveryComputer-based at Pearson VUE; closed-book with on-screen NCEES PS Reference Handbook
PassingPass/fail; cut score set by NCEES (no published numeric score)
ReferencesOn-screen NCEES PS Reference Handbook only — no personal materials
Content AreaWeightQuestionsKey Topics
1. Legal Principles~22%~22Hierarchy of calls, BFP/recording acts, easements, riparian rights
2. Professional Survey Practices~22%~22Boundary retracement, monumentation, evidence, witness/lost corners
3. Standards & Specifications~22%~22BLM Manual, ALTA/NSPS, FGCS accuracy standards, ROS contents
4. Business Practices~17%~17Ethics, professional conduct, expert witness, liability, records
5. Areas of Practice~17%~17Subdivision platting, topographic, construction, GIS/photogrammetric oversight
Time Management Strategy (PS, ~7h test time)
  • 100 questions in ~420 minutes ≈ 4.2 minutes per question.
  • Computer-based with one 50-minute scheduled break between halves.
  • Use the searchable on-screen NCEES PS Reference Handbook — practice with it before exam day.
  • Apply common-law principles only — do not rely on state-specific statutes.
  • No penalty for guessing — never leave a question blank.
  • Legal Principles + Professional Practices ≈ 44% of the exam — emphasize boundary law mastery.
NCEES PS Reference Handbook (key tabs)
Surveying conventions & symbolsCoordinate geometry (COGO)Horizontal & vertical curvesTraverse & least-squaresPhotogrammetry / LiDARDatums, projections, geoidState Plane (Lambert / TM)BLM PLSS — sections, restorationStatistics & error propagationBoundary law / hierarchy of calls

Available on-screen during the exam at NCEES Pearson VUE delivery; download the latest edition from ncees.org for study.

2. Key Formulas

Traverse, area, curves, GPS, errors

Traverse Computations

Latitude:
Departure:
Closure Error:
Precision Ratio:
Compass Rule (Lat):
Compass Rule (Dep):

Area Computations

Coordinate Method:
DMD Method:
Trapezoidal Rule:
(equal spacing h)
Simpson's 1/3:
(odd # ordinates)

Horizontal Curves

Degree of Curve:
(arc definition)
Tangent:
Length:
(or 100 * Delta/D)
External:
Mid Ordinate:
Long Chord:
PC Station:
PT Station:
Horizontal curve elements: PI, PC, PT, R, T, L, E, M, LC, and delta labeled

Vertical Curves

Rate of change:
(g in %, L in stations)
Elevation on curve:
High/low point:
(from BVC)
Offset from tangent:
(at midpoint; g in %, L in stations)

GPS Heights

Height relationship:
(ellipsoid = ortho + geoid)
Orthometric height:
Geoid undulation:
GPS height relationship: Earth surface, ellipsoid, and geoid with h, H, and N labeled

Scale / Grid-Ground Factors

Elevation factor:
(R = Earth radius, h = elevation)
Grid factor:
(varies with distance)
Combined factor:
Grid distance:

Error Theory & Statistics

Std deviation:
Std error of mean:
Error propagation (+/-):
Error propagation (*):
(Q = a*b)
Weighted mean:
(w = 1/sigma^2)
68-95-99.7 rule:

Photogrammetry

Photo scale:
(f = focal length, H = flying height)
Relief displacement:
(r = radial dist, h = obj height)
Flying height (AGL):
(for desired scale S)
Ground coverage:

3. Evidence Hierarchy & Boundary Rules

Common law hierarchy, retracement, unwritten rights

Hierarchy of Calls (Common Law / Brown's Ch. 5-6)
  1. Lines actually run on the ground - corners established, monuments set, lines marked by creating surveyor
  2. Natural monuments - rivers, lakes, ridges, trees
  3. Artificial monuments - stakes, pipes, stones set on ground
  4. Adjoiners / record boundaries - calls for adjoining tracts, senior rights
  5. Courses / bearings - direction of boundary lines
  6. Distances - measured lengths of lines
  7. Area / quantity - acreage or square footage (lowest weight)

Intent of the parties is the overriding principle governing all elements.

Evidence Hierarchy Pyramid
7 bands: top = Lines Actually Run (highest), bottom = Area (lowest)
Monument TypeExamplesRelative Weight
NaturalRivers, lakes, trees, ridges, rock outcropsHighest
Artificial (original)Original stakes, stones, mounds set by surveyorHigh
Artificial (subsequent)Iron pipes, rebar, mag nails set laterMedium-High
RecordCalls to adjoining tracts, recorded platsMedium
Accessory/witnessBearing trees, reference marksSupport only
7 Rules of Construction
  1. Intent of the parties controls
  2. The deed is construed most strongly against the grantor
  3. A grant is always construed in favor of the grantee
  4. The whole instrument is considered, not isolated parts
  5. Specific descriptions prevail over general ones
  6. Where two clauses are irreconcilable, the LATER clause typically prevails (majority rule); a few states (notably CA) follow the opposite "first-clause" rule
  7. Monuments prevail over courses, courses over distances, distances over area
Retracement Principles
  • Follow the footsteps of the original surveyor
  • The retracing surveyor has NO authority to establish new corners
  • Original monuments, when found, are conclusive (even if imprecise)
  • Proportionate measurement used when original corners are lost
  • An obliterated corner can be restored from evidence; a lost corner cannot
  • Obliterated = position can be determined from evidence
  • Lost = position cannot be determined beyond reasonable doubt
Unwritten RightKey RequirementsTime Period
Adverse PossessionOpen, notorious, continuous, hostile, exclusive, under claim of right (tax payment is required only in a minority of states, e.g., CA)Varies by state (10–20 yrs typical)
Prescriptive EasementOpen, notorious, continuous, hostile use (NO tax payment needed, NO exclusivity needed)Varies by state (10–20 yrs typical)
Agreed BoundaryUncertainty + agreement (express or implied) + acquiescence + change in positionNo fixed period
Boundary by AcquiescenceOccupation to visible line with implied agreementStatute of limitations
Boundary by EstoppelRepresentation + reliance + injury if boundary changedNo fixed period
Practical LocationActs on the ground showing where parties treated boundaryLong period of time
Water Boundary Rules
  • Accretion - Gradual, imperceptible additions of land by water action; boundary moves with water
  • Reliction - Gradual recession of water; exposed land goes to riparian owner
  • Avulsion - Sudden, perceptible change; boundary remains at original location
  • Erosion - Gradual wearing away; boundary moves with the water
  • Navigable waters: public trust doctrine applies (state owns bed below ordinary high water)
  • Non-navigable: riparian owner typically owns to thread (center) of stream

5. PLSS Reference

Sections, corners, proportionate measurement

Township & Range System
  • Township: 6-mile square area (36 sections of ~640 acres each)
  • Range: Column of townships E/W of a principal meridian
  • Township line: E-W line at 6-mile intervals from baseline
  • Range line: N-S line at 6-mile intervals from principal meridian
  • Notation: T3N, R5W = Township 3 North, Range 5 West
  • 37 federal Principal Meridians cover the PLSS area; each governs the surveys within its territory.
Township Grid Diagram
T/R grid showing baselines and principal meridian, numbered townships
Section Numbering (Serpentine from NE)
6
5
4
3
2
1
7
8
9
10
11
12
18
17
16
15
14
13
19
20
21
22
23
24
30
29
28
27
26
25
31
32
33
34
35
36

Numbering begins at NE corner (Section 1), proceeds W to Section 6, then drops and goes E (Section 7-12), etc.

Standard Subdivision of Sections
  • Section = ~640 acres (1 mile square)
  • Quarter section = ~160 acres (1/2 mile square): NE 1/4, NW 1/4, SE 1/4, SW 1/4
  • Quarter-quarter = ~40 acres (1/4 mile square): NE 1/4 of NW 1/4, etc.
  • Read descriptions from smallest to largest: “NE 1/4 of SW 1/4 of Sec. 12”
  • Fractional sections occur along N and W township boundaries due to convergence
Quarter Section Subdivision Diagram
Section divided into 4 quarters, then each quarter into 4 quarter-quarters, with acreages labeled
Corner TypeDescriptionLocation
Township cornerIntersection of township and range linesEvery 6 miles
Section cornerIntersection of section linesEvery 1 mile (interior)
Quarter-section cornerMidpoint of section lineEvery 1/2 mile
Meander cornerWhere section/township line meets navigable waterIrregular
Witness cornerSet near a true corner when corner cannot be placedNear true point
Closing cornerWhere survey line meets previously established lineAt intersection
Angle pointWhere a boundary changes directionAs needed
Proportionate Measurement
  • Single proportion: For corners on a line between two existing corners (e.g., quarter corners)
  • Double proportion: For corners at intersection of two lines (e.g., section corners) - use both N-S and E-W controls
  • Apply proportionate measurement only when corner is lost, never when obliterated
  • Lost corner: position cannot be determined beyond reasonable doubt from any evidence
  • Obliterated corner: position CAN be determined from evidence (accessories, witnesses, field notes)
  • Original corners, when found, are always controlling regardless of precision

6. Datums & Projections

Horizontal/vertical datums, State Plane, geoid models, grid-ground

Horizontal DatumYearEllipsoidKey Facts
NAD271927Clarke 1866Origin: Meades Ranch, KS. Astronomic; non-geocentric.
NAD83 (1986)1986GRS80Geocentric; ~250,000 stations; multiple realizations after.
NAD83 (2011)2011GRS80Current operational realization; CORS-based; epoch 2010.00.
WGS841984+WGS84GPS native datum; ~ NAD83 at meter level (modern realizations differ ~1–2 m).
NATRF2022TBDGRS80Plate-fixed replacement for NAD83; time-dependent positions.
State Plane Coordinate System (SPCS)
  • Designed to keep scale distortion within ~1:10,000 over a zone.
  • Each state has one or more zones; zone boundaries are county-aligned.
  • Lambert Conformal Conic for zones that extend primarily east–west (most states).
  • Transverse Mercator for zones that extend primarily north–south (e.g., NJ, IL east, NH).
  • Oblique Mercator for zones that trend diagonally (Alaska Zone 1).
  • Coordinates are grid coordinates; adjust by combined factor for ground distances.

Geoid & Ellipsoid Heights

Ellipsoid → orthometric:
(H = orthometric (NAVD88), h = ellipsoid (GPS), N = geoid undulation)
Earth radius (mean):
(NCEES handbook value (Clarke 1866 mean))
Vertical DatumYearKey Facts
NGVD29192926 tide gauges; mean sea level approximation; obsolete for new federal work.
NAVD881988Single tide gauge (Father Point, Rimouski, Quebec); geopotential; current standard.
NAPGD2022TBDComing replacement for NAVD88; geoid-based and GNSS-accessible.
IGLD851985Great Lakes datum; differs from NAVD88 by basin.
Geoid Models & the GPS Workflow
  • GEOID18 (current): converts NAD83(2011) ellipsoid heights to NAVD88 orthometric heights.
  • Geoid undulation N varies regionally; in CONUS roughly −53 m (West) to −22 m (East).
  • GPS measures ellipsoid height h; GEOID model gives N; compute H = h − N for elevation.
  • Always check the geoid-model epoch matches the project datum; mixing produces meter-level errors.

Grid–Ground Conversion

Elevation factor:
(R ≈ 20,906,000 ft = 6,371,000 m (NCEES handbook))
Combined factor:
(k = grid scale factor at the project area)
Grid distance:
Ground distance:
ConversionValue
1 US survey foot1200/3937 m = 0.3048006096… m
1 international foot0.3048 m exactly (since 2023, NIST defines all federal feet as international)
1 meter3.280833… US survey feet
1 chain (Gunter)66 ft = 4 rods = 100 links
1 link0.66 ft = 7.92 in
1 rod / pole / perch16.5 ft = 1/4 chain
1 acre43,560 sq ft = 10 sq chains
1 section640 acres (nominal)
1 mile5,280 ft = 80 chains

7. Key Definitions

Boundary, surveying, and legal terms

Boundary & Evidence Terms

Monument - Physical object marking a survey point (natural or artificial)
Bearing tree - Tree marked as accessory to identify/witness a corner
Meander line - Line run near a body of water to approximate its boundary (not the boundary itself)
Riparian - Relating to land abutting a stream or river
Littoral - Relating to land abutting a lake, ocean, or sea
Accretion - Gradual deposit of soil by water; boundary moves with shoreline
Avulsion - Sudden change in watercourse; boundary stays at original location
Reliction - Land exposed by gradual recession of water
Privity - Successive relationship between parties to the same property rights
Tacking - Adding successive periods of possession (e.g., for adverse possession)
Senior right - Earlier conveyance; takes priority over junior (later) grant
Junior right - Later conveyance; yields to senior right where conflict exists
Parol evidence - Oral testimony about intent, circumstance, or meaning of a deed
Patent - Government grant of public land to a private party
Ambulatory boundary - Boundary that moves with the feature it follows (water)
Fixed boundary - Boundary that does not move regardless of feature changes
Excess/deficiency - Parcel is larger/smaller than record calls; apportioned pro rata
Simultaneous conveyance - All lots in a plat conveyed at once; all have equal rights
Sequential conveyance - Lots sold one at a time; earlier grantees have senior rights
Bona fide rights - Rights acquired in good faith, for value, without notice of defect

Surveying & Measurement Terms

Azimuth - Horizontal angle measured clockwise from north (0-360)
Bearing - Horizontal angle from N or S toward E or W (0-90 per quadrant)
Zenith angle - Vertical angle from directly overhead (0 = straight up, 90 = horizontal)
Deflection angle - Angle from extension of previous line to next line (R or L)
Backsight - Sighting to a previously established point for orientation
Foresight - Sighting to a new point to be established
Turning point (TP) - Temporary point used in leveling for instrument setup
Benchmark (BM) - Permanent point with established elevation
Height of instrument (HI) - Elevation of the line of sight above datum
Closure error - Distance between computed and known end position of a traverse
Precision ratio - Ratio of closure error to total traverse length (e.g., 1:10,000)
EDM - Electronic Distance Measurement - measures distances using light/radio waves
Total station - Instrument combining EDM, digital theodolite, and data collector
GNSS/GPS - Global Navigation Satellite System for 3D positioning
RTK - Real-Time Kinematic: cm-level GNSS with real-time corrections
PDOP - Position Dilution of Precision; lower is better satellite geometry
Multipath - Signal reflection causing positioning errors
Ellipsoid height (h) - Height above the reference ellipsoid (from GNSS)
Orthometric height (H) - Height above the geoid (mean sea level approximation)
Geoid undulation (N) - Separation between ellipsoid and geoid; h = H + N

Legal & Professional Terms

Fee simple - Absolute ownership of real property; highest estate
Easement - Right to use another's land for a specific purpose
Appurtenant easement - Attached to the land; transfers with property (dominant/servient)
Easement in gross - Personal right; not tied to land ownership (e.g., utility easement)
Prescriptive easement - Easement by adverse use: open, notorious, hostile, continuous (5 yr CA)
Right-of-way - Right to pass over another's land; or the strip of land itself
Encroachment - Unauthorized intrusion of a structure onto neighboring property
Encumbrance - Any claim or restriction on the title (liens, easements, restrictions)
Covenant - Agreement in a deed restricting land use
Dedication - Voluntary transfer of private land for public use
Eminent domain - Government power to take private property for public use (with compensation)
Adverse possession - Acquiring title by open, notorious, continuous, hostile, exclusive possession; statutory period 10–20 yr typical (state-by-state)
Quiet title action - Court proceeding to establish or settle title to property
Lis pendens - Notice of pending lawsuit affecting title to real property
Chain of title - Sequence of historical transfers of title to a property
Cloud on title - Any outstanding claim that could impair the owner's title
Quitclaim deed - Transfers whatever interest grantor has; no warranties
Grant deed - Common deed form transferring fee title with limited implied warranties (varies by state)
Warranty deed - Transfers title with full guarantees against all claims
ALTA survey - American Land Title Association survey; standard for title insurance
Subdivision - Division of land into parcels for sale, lease, or financing
Plat / final plat - Recorded subdivision map; specific procedures and thresholds set by state law
Record of Survey - Filed survey document required by most states when discrepancies are discovered or new monuments set; specific contents and trigger conditions vary
ALTA/NSPS Land Title Survey - Boundary survey performed to ALTA/NSPS Standards (latest edition) for title-insurance purposes
Basis of bearings - Reference system for all bearings on a survey (e.g., record map, GPS)
Standard of care - Level of skill/diligence expected of a competent surveyor
Statute of limitations - Time limit to bring a legal action; varies by claim type