Lesson 4

Safety Procedures

Learning Objectives

After completing this topic, you should be able to:

  • Identify OSHA requirements applicable to surveying operations
  • Develop site-specific safety plans and hazard assessments
  • Apply traffic control principles for roadway work zones
  • Explain the 811 utility locating process and legal requirements
  • Specify appropriate personal protective equipment (PPE) for various field conditions
  • Recognize environmental, biological, and site-specific hazards
  • Understand employer and employee safety responsibilities

Overview

Field surveying is inherently hazardous work. Surveyors operate in active construction zones, along busy roadways, in remote terrain, and near underground and overhead utilities. OSHA statistics consistently rank construction-related activities among the most dangerous occupations. The PS exam tests your knowledge of safety regulations, hazard assessment, and risk mitigation procedures -- not as a secondary concern, but as a core professional competency.

A surveyor who cannot manage field safety risks is not qualified to manage a survey project.


OSHA Regulatory Framework

Federal OSHA

The Occupational Safety and Health Administration (OSHA) sets minimum safety standards for all workplaces. Key regulations affecting surveying:

StandardCitationApplication
General Duty ClauseSection 5(a)(1)Employers must provide a workplace free from recognized hazards
Construction Standards29 CFR 1926Applies when surveying on construction sites
General Industry Standards29 CFR 1910Applies to office operations and non-construction field work
Excavation Standard29 CFR 1926 Subpart PTrenching and excavation safety
Fall Protection29 CFR 1926 Subpart MProtection from falls over 6 feet
Electrical Safety29 CFR 1926 Subpart KWorking near energized conductors
Hazard Communication29 CFR 1910.1200Chemical exposure information

State OSHA Programs

Twenty-two states and territories operate their own OSHA-approved programs. These must be at least as stringent as federal OSHA and may impose additional requirements. Surveyors must comply with whichever standard is more protective.

Employer Responsibilities

Under OSHA, employers must:

  1. Provide a safe workplace free from recognized hazards
  2. Comply with all applicable OSHA standards
  3. Provide safety training appropriate to job hazards
  4. Provide required PPE at no cost to employees
  5. Maintain records of work-related injuries and illnesses (OSHA 300 Log)
  6. Post required OSHA notices in the workplace
  7. Report fatalities within 8 hours and hospitalizations within 24 hours

Employee Responsibilities

Employees must:

  1. Comply with all applicable safety rules and regulations
  2. Use provided PPE properly
  3. Report hazardous conditions to the employer
  4. Report work-related injuries and illnesses
  5. Not tamper with safety devices or equipment

Hazard Assessment

Job Hazard Analysis (JHA)

A Job Hazard Analysis is a systematic process for identifying and mitigating worksite hazards before work begins:

StepActionExample
1. Identify tasksList the tasks to be performedMonument search in roadway median
2. Identify hazardsFor each task, identify potential hazardsTraffic, overhead lines, underground utilities
3. Assess riskRate likelihood and severityHigh-speed traffic = high likelihood, severe consequence
4. Determine controlsIdentify measures to eliminate or reduce riskTraffic control plan, lane closure, high-visibility apparel
5. DocumentRecord the JHA and communicate to all crew membersWritten JHA reviewed at tailgate meeting

Figure PS.4.6 — Hierarchy of Safety Controls

Hierarchy of Controls

OSHA's hierarchy of controls, from most effective to least effective:

LevelControl TypeSurveying Example
1. EliminationRemove the hazard entirelySchedule work when roadway is closed
2. SubstitutionReplace with a less hazardous alternativeUse GNSS instead of total station to reduce time in traffic
3. Engineering controlsIsolate workers from the hazardTraffic barriers, delineators, temporary barriers
4. Administrative controlsChange work practicesLimit time in hazard zone, buddy system, training
5. PPEProtect the individual workerHigh-visibility vest, hard hat, safety glasses

PPE is the last resort, not the first. Effective safety programs address hazards at the highest feasible level.

Tailgate Safety Meetings

Before each day of field work, the party chief should conduct a brief safety meeting covering:

  • Specific hazards at the day's work site
  • Traffic control plan (if applicable)
  • PPE requirements
  • Emergency procedures and contact numbers
  • Communication protocols
  • Weather conditions and precautions
  • Any changes from previous days

Traffic Control

Work Zone Components

Per the Manual on Uniform Traffic Control Devices (MUTCD), work zones consist of four areas:

ZonePurposeElements
Advance Warning AreaAlert approaching motoristsWarning signs at prescribed spacing
Transition AreaGuide traffic around the work areaTapers using cones, barrels, or delineators
Activity AreaProtect workers and equipmentBuffer space plus work space
Termination AreaReturn traffic to normal patternsEnd construction signs, taper

Taper Lengths

Taper length depends on posted speed and lane width:

Speed LimitMinimum Taper Length (per lane)
25 mph75 feet
35 mph175 feet
45 mph360 feet
55 mph540 feet
65 mph720 feet

Actual taper lengths should be calculated using the MUTCD formula: L = (speed squared) / 60 for speeds above 40 mph, or L = width x speed / 2 for speeds at or below 40 mph.

Surveyor-Specific Traffic Control

Surveying operations present unique traffic control challenges:

  • Mobile operations -- Surveyors frequently move along roadways, making fixed work zones impractical
  • Short-duration occupancy -- A few minutes at each setup does not justify full lane closure
  • Shoulder work -- Often the only practical location for control points and boundary monuments

Minimum protection for mobile operations:

  • Vehicle-mounted warning signs or arrow boards
  • Vehicle emergency flashers
  • High-visibility apparel (Class 2 minimum; Class 3 for high-speed roads)
  • Shadow vehicle positioned upstream of work area
  • Rotating beacon or strobe lights on survey vehicles

Flagger Operations

When flaggers are required:

  • Must be trained and certified (in most jurisdictions)
  • Must wear Class 3 high-visibility apparel
  • Must use STOP/SLOW paddle (minimum 18 inches)
  • Must be positioned with adequate sight distance
  • Must have an escape route

Underground Utility Locating

The 811 System

The national 811 "Call Before You Dig" system is the primary mechanism for preventing underground utility damage:

StepActionTiming
1. Call 811Contact the one-call centerAt least 2-3 business days before excavation (varies by state)
2. Provide informationLocation, type of work, extent of excavationAt time of call
3. Receive ticketConfirmation number for trackingImmediately
4. Wait for marksUtility owners mark their facilitiesWithin the notification period
5. Respect marksHand dig within the tolerance zoneDuring excavation

Utility Marking Standards (APWA Uniform Color Code)

ColorUtility Type
RedElectric power lines, conduit, cables
YellowGas, oil, steam, petroleum
OrangeCommunications, alarm, signal lines, cable TV
BluePotable water
GreenSewer and storm drain
PurpleReclaimed water, irrigation
PinkTemporary survey markings
WhiteProposed excavation outline

Surveyor Applicability

Surveyors must call 811 when:

  • Setting monuments that require excavation below the surface
  • Driving posts or pipes deeper than typical stake depth
  • Core drilling or augering for monument installation
  • Any subsurface disturbance that could contact utilities

Tolerance Zone

The tolerance zone is the area around a marked utility within which hand digging (or other careful methods) is required. Typical tolerance zones are 18-24 inches on either side of the mark, but this varies by state.


Personal Protective Equipment (PPE)

Minimum PPE by Work Environment

EnvironmentRequired PPE
Active construction siteHard hat, safety glasses, high-visibility vest, safety-toe boots
Roadway work zoneHigh-visibility apparel (Class 2 or 3), safety glasses
General field workAppropriate footwear, sun protection, seasonal clothing
Near waterPersonal flotation device (PFD) when working from boats or near deep water
Near heavy equipmentHard hat, hearing protection, high-visibility apparel
Confined spacesAtmospheric monitoring, retrieval harness, attendant

High-Visibility Apparel Classes

ClassMinimum Background MaterialMinimum Retroreflective MaterialApplication
1217 sq in155 sq inLow-traffic areas, parking lots
2775 sq in201 sq inMost survey field work
31240 sq in310 sq inHigh-speed roadways, low-visibility conditions

Hearing Protection

Noise levels requiring hearing protection (85 dBA over 8-hour TWA):

Surveyors may encounter excessive noise near:

  • Heavy construction equipment
  • Pile driving operations
  • Pavement sawcutting
  • Demolition activities
  • Generators and compressors

Environmental Hazards

Heat Illness

Heat illness is a serious risk for outdoor workers. The progression from heat stress to heat stroke can be rapid:

ConditionSymptomsResponse
Heat crampsMuscle cramps, heavy sweatingMove to shade, hydrate, rest
Heat exhaustionHeadache, nausea, weakness, heavy sweating, cool/clammy skinMove to cool area, loosen clothing, hydrate, seek medical attention if symptoms worsen
Heat strokeConfusion, hot/dry skin, rapid pulse, loss of consciousnessMedical emergency -- call 911, cool the person immediately

Prevention:

  • Acclimatize new workers gradually (over 7-14 days)
  • Provide water (at least one quart per hour in hot conditions)
  • Schedule heavy work for cooler parts of the day
  • Provide shade for rest breaks
  • Train all workers on heat illness recognition

Cold Stress

Cold-related hazards include:

  • Hypothermia -- Core body temperature drops below 95 degrees F
  • Frostbite -- Tissue freezing, especially extremities
  • Trench foot -- Prolonged wet/cold exposure to feet

Prevention:

  • Layer clothing (wicking base, insulating mid, waterproof outer)
  • Protect extremities (insulated gloves, warm headwear)
  • Take warming breaks
  • Monitor each other for symptoms
  • Keep dry clothing available

Biological Hazards

Common biological hazards in field surveying:

HazardRiskPrevention
TicksLyme disease, Rocky Mountain spotted feverPermethrin-treated clothing, daily tick checks, long pants tucked into boots
Venomous snakesEnvenomationWatch where you step and reach, wear boots, carry a first aid kit
Poison ivy/oak/sumacContact dermatitisLearn to identify, wear long sleeves, wash exposed skin promptly
Stinging insectsAllergic reactions, anaphylaxisCarry epinephrine if allergic, avoid disturbing nests
MosquitoesWest Nile virus, other diseasesUse repellent, wear long sleeves in infested areas

Overhead Power Line Safety

Minimum Approach Distances

When working near overhead power lines, maintain minimum clearance:

Voltage RangeMinimum Clearance
Up to 50 kV10 feet
50 kV to 200 kV15 feet
200 kV to 350 kV20 feet
350 kV to 500 kV25 feet
500 kV to 750 kV35 feet

Surveyor-Specific Considerations:

  • Prism poles and GNSS antennas extend the worker's reach -- add the height of the pole to the person's reach
  • Metal range poles and leveling rods are conductive
  • Guy wires on utility poles may be energized if insulation has failed
  • Survey equipment on tripods near power lines increases risk

Common wrong path — forgetting pole/antenna height when judging overhead clearance. Minimum approach distances to energized overhead lines are measured from the highest point of the worker or the longest conductive object the worker is holding or carrying — not from the worker's body or feet. A surveyor holding an 8-ft range pole or a GNSS survey pole with antenna must add the pole's length to their own height when judging clearance. Students sometimes answer "10 ft" to an overhead clearance question without accounting for the equipment, producing a dangerously wrong clearance calculation. OSHA and utility operators assess approach distance from the closest conductive object the worker can extend — metal range poles, leveling rods, and GNSS antennas all count. Exam questions test this by describing a setup where the person is 6 ft tall but their pole reaches 14 ft; the approach clearance must account for the pole.

Quick retrieval check — try before reading on.

A 6-foot-tall surveyor is using a 14-foot prism pole on a project near a 12 kV overhead distribution line. The minimum approach distance for up to 50 kV is 10 feet. What clearance must the surveyor maintain?

The measurement is from the highest point of the surveyor or their equipment, whichever is closer to the line. In this case, the prism pole is the limiting dimension. If the surveyor holds the pole vertically above their head, the top of the pole is at approximately 6 ft (surveyor height) + 14 ft (pole length) ≈ 20 ft above the ground (accounting for where the pole is gripped).

To maintain the 10-ft minimum approach distance, every point on the pole must remain at least 10 ft from the line in any direction. If the line sags to 25 ft above ground and the pole's top reaches 20 ft, vertical clearance is only 5 ft — well inside the minimum. The surveyor must either lower the pole, move horizontally away from the line, or in high-voltage areas, contact the utility for a safety standby (temporary de-energization or observation). The safe practice: visually estimate the line height, add a generous safety margin, and when in doubt, call the utility. Metal equipment, pole-mounted antennas, and leveling rods are all conductive — the 10-ft rule is measured from the closest conductive extension, not from the worker's feet.


Exam Tips

  • OSHA questions on the PS exam focus on practical application, not citation numbers -- know the concepts
  • Understand the hierarchy of controls (elimination, substitution, engineering, administrative, PPE) and that PPE is the last resort
  • Know the APWA utility marking color code -- this is frequently tested
  • Traffic control questions test your knowledge of work zone components and when flaggers are required
  • Heat illness prevention is a common exam topic -- know the progression and appropriate responses
  • Understand that employer responsibilities include providing PPE at no cost and maintaining injury records
  • The 811 system and its requirements are testable -- know the process and timing

Related Test Topics

  • Project Planning and Management (Topic 4.1)
  • Quality Assurance and Quality Control Methods (Topic 4.5)
  • Risk Management (Topic 4.6)
  • Professional Conduct and Ethics (Topic 4.7)

Further Reading